Contingent Consideration: s51 FA2003 Guide
Where part of the purchase price depends on a future event, s51 FA2003 requires SDLT to be calculated on the full assumed amount, including the contingent element. However, s90 FA2003 may allow deferral of the contingent portion. Refunds are available if the contingency never occurs, but timing rules are strict.
Last verified: 29 August 2026
Key Takeaways
- •Under s51 FA2003, contingent consideration is assumed to be payable, so SDLT must be calculated on the full amount at the effective date
- •Section 90 FA2003 allows buyers to apply to HMRC to defer payment of the SDLT on the contingent element where it is payable more than 6 months after the effective date
- •If the contingency never triggers, the excess SDLT is recoverable. The amendment route runs for 12 months after the filing date of the original return, not for 12 months from the date the contingency falls away
- •Once the amendment window closes, s80(4)(b) FA2003 still allows a claim for repayment, made under the Sch 11A claims machinery. Overpayment relief in Sch 10 para 34 is a different provision, capped at 4 years from the effective date, and the para 34A exclusions will usually block it while the s80 route remains open
- •Interest runs from the effective date of the transaction, not the date the contingency triggers or is assessed
- •Contingent and uncertain consideration are both dealt with by s51 FA2003, in different ways, and s80 FA2003 is the adjustment mechanism for both. The distinction that matters is between the two types of consideration, not between two sections
What Is Contingent Consideration?
Contingent consideration arises where all or part of the purchase price for a property is conditional on a specified future event occurring or not occurring. The payment obligation exists, but it is dependent on something happening, such as planning permission being granted, a tenant vacating, a business achieving certain turnover targets, or a remediation certificate being issued.
Section 51 FA2003 governs contingent consideration. The core rule is that for the purpose of calculating SDLT at the effective date of the transaction, contingent consideration is assumed to be payable. It does not matter that the event may never occur; at the moment of filing the return, HMRC requires you to include the contingent element in full.
Definition: Consideration is "contingent" if it is payable only if a stated event occurs or does not occur. The key is that you know the amount upfront; you just don't know whether it will be paid. If you do not know the amount either, the consideration is "uncertain" or "unascertained", which s51 also covers, and which is valued on a reasonable estimate rather than an assumed outcome.
Treatment at the Return Date
The land transaction return (SDLT1) must be filed within 14 days of the effective date of the transaction, which is the date of completion, or the date of substantial performance where the contract is substantially performed before completion. Exchanging contracts is not itself the effective date. At this point, SDLT must be paid on the total assumed consideration, which includes:
- The fixed, certain base consideration
- The full contingent amount, assumed to be payable regardless of probability
HMRC's treatment is binary in terms of the assumption: you assume 100% of the contingent amount will be paid. There is no discounting for probability. A contingent payment of £100,000 that is only 10% likely to occur is still treated as £100,000 for SDLT at the effective date.
The full contingent amount must be included in the SDLT1 return filed within 14 days. Omitting it, even on the basis that you believe it is unlikely to be triggered, constitutes an incorrect return and may attract penalties and interest.
Deferring Payment: s90 FA2003
While s51 requires the full contingent amount to be included in the SDLT calculation at the effective date, s90 FA2003 provides a significant cash flow benefit. Where the contingent (or uncertain) consideration is payable more than 6 months after the effective date of the transaction, the buyer can apply to HMRC to defer payment of the SDLT attributable to that contingent element.
This means the buyer still declares the full assumed consideration on the SDLT1 return, but applies to defer the portion of SDLT that relates to the contingent element rather than paying it all upfront.
Key Requirements for s90 Deferral
- Timing of the contingent payment: The contingent consideration must be payable more than 6 months after the effective date of the transaction. If the contingency could trigger within 6 months, deferral is not available.
- Application deadline: The application to defer must be made before the normal filing deadline for the SDLT return (14 days after the effective date). A late application will not be accepted.
- HMRC discretion: HMRC can approve the deferral with conditions. These may include requirements to notify HMRC if circumstances change, or to pay the deferred amount within a specified period once the contingency triggers.
- Interest still accrues: Deferral does not eliminate the interest charge. Interest on the deferred SDLT amount runs from the effective date. If the contingency triggers years later, the accrued interest will be payable alongside the deferred SDLT.
Cash flow benefit: On a large contingent payment, the s90 deferral can free up significant capital. For example, on a £100,000 contingent element attracting 5% marginal SDLT, deferral keeps £5,000 in the buyer's hands until the contingency triggers or falls away. If the contingency never triggers, the deferred SDLT is not payable and no interest is due on that element.
Do not confuse deferral with exemption. A s90 deferral postpones when the SDLT is paid; it does not reduce or eliminate the SDLT liability. If the contingency eventually triggers, the full deferred SDLT plus accrued interest becomes payable. Always model the potential interest cost when deciding whether to apply for deferral.
Worked Example: Planning Permission Contingency
A buyer purchases a property for £400,000, with a further £100,000 payable if planning permission for residential development is granted within 5 years of completion.
SDLT Calculation at Effective Date
What Happens Next
If planning IS granted
The contingency triggers. The buyer pays the £100,000 to the seller. No additional SDLT is due, because it was already paid. The SDLT return does not need to be amended.
If planning is NOT granted
SDLT is recalculated on just £400,000 and HMRC refunds £5,000, the excess SDLT paid. Inside the amendment window you amend the return under Sch 10 para 6. Outside it, you claim repayment under s80(4)(b).
Refund if Contingency Never Triggers
Section 80 FA2003 is the adjustment mechanism. It applies where the contingency occurs, or where it becomes clear that it will not occur. Where less tax turns out to be payable, s80(4) gives the buyer two routes to recover the excess, and which one is open depends entirely on the calendar. Inside the amendment window, the buyer amends the original return under Sch 10 para 6 FA2003. Once that window has closed, the buyer makes a claim to HMRC for repayment of the amount overpaid under s80(4)(b).
The amendment window is 12 months after the filing date of the original land transaction return (Sch 10 para 6(3) FA2003), and that filing date is 14 days after the effective date. It runs from the original return, not from the date the contingency falls away. In the planning permission example, a refusal that becomes final inside that first year lets the buyer file an amended SDLT1 on HMRC's online portal, recalculating SDLT on the base consideration only and claiming the refund. A refusal that becomes final after 4 years, once all appeal rights are exhausted, arrives long after the amendment window has shut, so the claim has to be made under s80(4)(b) instead.
The amended return must show the correct SDLT on the reduced consideration, and the refund is typically processed within 30 days of HMRC receiving the amended return, though complex cases may take longer.
Measure the window from the original return, not from the contingency. The 12-month amendment window runs from the filing date of the original land transaction return. On any contingency with a horizon longer than about a year, expect that window to be shut before you know the outcome, and plan for the s80(4)(b) claim set out below.
Taking a new lease? You pay stamp duty on the rent too
Lease stamp duty is worked out from the rent over the whole term. A specialist checks the figure before you sign.
Outside the Amendment Window: the s80(4)(b) Claim
Where the amendment window has closed, s80(4)(b) FA2003 still allows the purchaser to make a claim to HMRC for repayment of the amount overpaid. HMRC's guidance is explicit about the mechanics: if the twelve-month window has expired, a claim under Schedule 11A FA2003 should be made (SDLTM50300). Schedule 11A is titled "stamp duty land tax: claims not included in returns". It is the claims machinery, covering the form of claim, the declaration, the records you must keep and HMRC's enquiry powers. It is not itself a relief, and it carries no time limit of its own.
The claim is made in the form HMRC determines, with a declaration that the particulars are correct, and Sch 11A para 2(4) bars a repayment claim unless you hold documentary evidence that the tax was paid. Expect to show that the contingency definitively did not occur, that the original return was filed on the assumption that it would, and what was actually paid. HMRC may ask for formal evidence of the failure of the contingency.
This route is often confused with overpayment relief, which is a different provision with a much harder edge. Overpayment relief sits in Sch 10 para 34 FA2003, and para 34B(1) provides that a claim "may not be made more than 4 years after the effective date of the transaction". The deadline is not the only restriction. Para 34A lists seven cases, A to G, in which HMRC is not liable to give effect to a claim. Case B applies where the claimant is or will be able to seek relief by taking other steps under the SDLT legislation. Case C applies where the claimant could have taken those steps within a period that has now expired and knew, or ought reasonably to have known, before the end of that period that the relief was available. A contingency refund sits squarely within what those two cases are aimed at, because s80 supplies the other steps. Treat overpayment relief as a separate regime, not as a way of rescuing a s80 claim you did not make in time. The point is not beyond argument, because the Upper Tribunal read the para 34A exclusions narrowly twice in 2026. In BTR Core Fund JPUT v HMRC [2026] UKUT 27 (TCC) it held that a rate error made after a relief had been validly claimed was not a mistake in the claim under Case A. In HMRC v Candy [2026] UKUT 282 (TCC) it held that para 34 is a standalone remedy of last resort that a mandatory statutory repayment route does not displace, and observed that Cases A and C would rarely apply in that situation. Neither decides the s80 position, where Case B is the live obstacle, so take advice rather than assuming the door is shut.
If your contingency has a long time horizon (for example, a 10-year development overage clause), keep records of the original SDLT return, the contract term creating the contingency and the full consideration breakdown. When the contingency fails you will need that documentation to support the claim, and by then the amendment route will almost certainly have closed.
Contingent vs Uncertain Consideration
Both types are dealt with by section 51 FA2003, which tells you how to value the consideration at the effective date. Contingent consideration is assumed to be payable. Uncertain or unascertained consideration, such as an overage clause depending on future rental income, planning units or market values, is valued on a reasonable estimate. Section 80 FA2003 is the adjustment mechanism that applies to both, once the contingency resolves or the amount becomes ascertained.
| Feature | Contingent (s51) | Uncertain or unascertained (s51) |
|---|---|---|
| Amount known? | Yes, fixed sum if triggered | No, depends on future formula |
| Trigger known? | Conditional on event occurring | Likely to occur, amount unclear |
| Initial SDLT | Full amount assumed payable | Reasonable estimate used |
| Subsequent adjustment | Amended return within 12 months | Further return within 30 days of ascertainment |
| Interest runs from | Effective date | Effective date (original transaction) |
In practice, many complex consideration arrangements have elements of both contingency and uncertainty. The correct characterisation of the consideration type affects the initial SDLT calculation methodology and the procedure for subsequent adjustments. Specialist advice should be sought in any case where the consideration structure is not straightforwardly fixed.
Interest Accrual
Whether the consideration was contingent or uncertain, interest on any underpaid SDLT runs from the effective date of the original transaction, not from the date the contingency triggers or the consideration is ascertained.
This is most relevant where the consideration was uncertain and the initial SDLT was calculated on a reasonable estimate and additional SDLT becomes due when the true amount is ascertained. HMRC will charge interest from the original effective date on the additional amount, even though the consideration was genuinely not known at that point. The interest is not a penalty but is statutory and cannot be appealed on the basis that the underpayment was not the taxpayer's fault.
Interest trap: On a large overage or earn-out, the interest running from the original effective date can represent a material cost. Interest runs on the unpaid tax, not on the consideration. On £500,000 of additional consideration falling in the 12% band, the extra SDLT is £60,000, and five years of interest at HMRC's current late payment rate of 7.75% adds roughly £23,250 on top. Always model the interest cost when structuring deferred consideration arrangements.
Common Pitfalls
Conflating s51 with s80
Many advisers apply the wrong provision depending on the structure. If the amount is known but payment depends on an event, s51 applies and the full amount is assumed payable immediately. Applying s80 instead (treating it as uncertain) would give a different initial SDLT calculation. The wrong characterisation leads to either overpayment or, more dangerously, underpayment with interest.
Measuring the refund window from the wrong date
The 12-month window for amending the return runs from the filing date of the original land transaction return, not from the date the contingency fails. On a long-dated contingency it will usually be closed by the time the outcome is known, so the claim goes in under s80(4)(b) instead. Buyers who assume a fresh 12 months starts when the contingency fails are relying on a window that was never open to them.
Not filing initially on the full assumed amount
Some buyers omit the contingent element from the initial SDLT return on the basis that the event "probably won't happen." This is an incorrect return. HMRC can raise an enquiry, charge the correct SDLT, plus interest and potential penalties for the incorrect return.
Frequently Asked Questions
How is contingent consideration treated for stamp duty?
Under s51 FA2003, contingent consideration is treated as if it will definitely be paid. You must include the full contingent amount in your SDLT calculation at the effective date of the transaction, regardless of how likely the contingency is to occur. SDLT is calculated on the total of fixed consideration plus the full contingent amount, and must be paid within 14 days.
Can I get a stamp duty refund if the contingency never happens?
Yes. If the contingency definitively fails, the excess SDLT is recoverable under s80 FA2003. Inside the amendment window, which runs for 12 months after the filing date of the original return, you amend the return under Sch 10 para 6 and HMRC refunds the excess. Once that window has closed you make a claim for repayment under s80(4)(b), which HMRC directs you to make under Schedule 11A. Overpayment relief under Sch 10 para 34 is a separate provision, limited to 4 years from the effective date and subject to the para 34A exclusions, so it is not a substitute for the s80 route.
What is the difference between contingent and uncertain consideration?
Contingent consideration is where you know the amount but payment depends on a future event, for example, £100,000 extra if planning is granted. Uncertain or unascertained consideration is where you know more will be payable but not how much, for example, a percentage of future rental income. Section 51 FA2003 values both at the effective date: the contingent amount is assumed to be payable in full, while an uncertain amount goes in at a reasonable estimate. Section 80 FA2003 is the adjustment mechanism for both, and once the contingency resolves or the amount is ascertained a further return is due within 30 days (s80(2A) FA2003).
Reviewed by

Julie White
ACASDLT Expert since 1999Stamp Duty Land Tax Specialist
ACA and Tax Adviser with a career spanning nearly four decades, specialising in SDLT planning and advisory work since 1999.
